The construction of the Industrial Complex for the production of silicon wafers (SW) and photovoltaic converters (PC) in the Industrial Park Chernyakhovsk is proceeding according to schedule.

  • The specialists of LMS Group, the general contractor, continue erecting the formwork, reinforcing and concreting the floor slabs, as well as the monolithic columns of the administrative and household complex of the SW. Backfilling of the building continued in the production and storage building of the SW.
  • In the production and storage building of PC the concrete floor preparation for the building is in progress.
  • The installation of the steel structures of the PC and SW production and storage buildings and the refrigeration center is in progress.
  • LMS specialists are engaged in reinforcement, concreting of the building floors and arrangement of concrete floor preparation of the technical gas and compressor building, as well as the cooling center.
  • Columns and foundations have been concreted in the structure of the fire-fighting station and distribution point, basement panels have been installed, and waterproofing has been applied.
  • On the territory of the checkpoint, the installation of steel structures, concrete floor preparation, the installation of outlets and masonry walls was completed.
  • At the hydrogen and oxygen generation station, the concrete preparation and building foundations have been poured.
  • On the territory of several buildings the specialists are busy with installation of profiled sheeting, as well as masonry of fire walls and partitions.

The customer of the project is EnCore Group, a part of the Unigreen Holding. Confirming a reputation of a reliable general contractor, LMS Group fulfills its obligations to the customers, who entrust us again with the implementation of their projects in a high-quality and timely manner.

Construction dynamics of the Chernyakhovsk Industrial Complex in May-photo-1 Construction dynamics of the Chernyakhovsk Industrial Complex in May-photo-2 Construction dynamics of the Chernyakhovsk Industrial Complex in May-photo-3 Construction dynamics of the Chernyakhovsk Industrial Complex in May-photo-4 Construction dynamics of the Chernyakhovsk Industrial Complex in May-photo-5 Construction dynamics of the Chernyakhovsk Industrial Complex in May-photo-6 Construction dynamics of the Chernyakhovsk Industrial Complex in May-photo-7 Construction dynamics of the Chernyakhovsk Industrial Complex in May-photo-8 Construction dynamics of the Chernyakhovsk Industrial Complex in May-photo-9 Construction dynamics of the Chernyakhovsk Industrial Complex in May-photo-10