CONSTRUCTION OF THE EASTERN EXIT TO THE FEDERAL HIGHWAY M-5 URAL
UFA

Project map - CONSTRUCTION OF THE EASTERN EXIT TO THE FEDERAL HIGHWAY M-5 URAL

PROJECT CHARACTERISTICS

1249 m
tunnel
470 m
bridge over the Ufa River
2200 m
flyover
47,7 m
bridge over Dolgoye Lake
FEDOROVKA-SHAKSHA
interchange
M5
interchange
5
overpasses and bridges
19
sewage treatment plants
1
charging point
1
service facility
22 700
vehicle capacity per day
2
two-lane lanes

ABOUT THE PROJECT

The implementation of the project for the construction of a regional highway of the Republic of Bashkortostan New exit from Ufa to the federal highway M-5 Ural – Eastern Exit includes three large-scale stages.

The first stage is a road tunnel, which includes two tunnels 1.2 km long, each with two lanes. The width of the road will be 8.5 m x 2.

The second stage is a steel bridge over the Ufa River with a length of 470 m and an overpass with a length of 2,200 m, with 2 two-lane platforms. The width of the roadway will be 27.7 m.

The third stage is a 12 km long highway with four lanes. The category of the road is IB (express). Road width is 26 m.

The Customers
Republic of Bashkortostan represented by the State Committee for Transport and Road Management Bashkir Concession Company, LLC
The General Contractor
Limakmarashchavtodorogi, LLC (GC Limak Marash)
Construction works commencement
February, 2020
Project deadline
September, 2023