As a result of the construction, the area of the new domestic airlines terminal will be 28,000 m2.
The new terminal at Mineralnye Vody International Airport will increase capacity to 1,000 passengers per hour and the total annual capacity to 3,800,000 passengers per year.
In addition to the turnkey construction of the new terminal building, the general contractor will lay utilities and communications networks, as well as work on the landscaping of the station square. The new terminal of domestic airlines will be equipped with five telescopic gangways, modern passenger service systems and baggage handling.
According to the contract with the general contractor the work is expected to begin in mid-April 2023 and will be completed in January 2025.