Video flyby from the drone of the Esplanada MFC in October

15.10.2021

Video fly by from the drone of the Esplanada MFC in October - Photo 1

At the Esplanade Multifunctional Center, 97% of all steel structures are installed. The installation of the roof of the building has been completed. Also, the installation of the profiled sheet has been completed. In total, construction work is ready on an area of 18 560 m².

  • At the moment, the installation of facade glazing is carried out on an area of 2 550 m², the readiness of work is 95%. For the installation of a decorative facade are being used PVC roofing membranes, porcelain stoneware tiles and a media facade. The installation area of PVC roofing membranes is 5 540 m².
  • Finishing work inside the building was carried out on an area of 16 793 m². On the site of future cinemas, walls of aerated concrete blocks are being erected. The total area of work at the moment is 6 864 m², the work is half finished. Floor screeds of 51 995 m² have been completed in the shopping area and entertainment center.
  • All 19 elevators have already been installed, as well as 4 travelators and 4 escalators.
  • The installation of the ventilation system is 94% complete, the heating system is 94%, the cooling system is 98% (6 842 tons of structures are used) and the fire system is 98% (41 000 tons of structures are used).