The reinforcement of the frame of the future Voronezh Airport terminal continues

15.09.2022

The construction of the new air terminal complex of Voronezh International Airport continues. The general contractor LMS Group strictly adheres to the approved work schedule.

  • The works on reinforcing and concreting of the terminal foundations, floor slab, vertical structures - walls and columns, foundation beams below the -0.150 mark, as well as the foundations for telescopic gangways have been completed.

    To perform the work LMS builders used 730 tons of steel structures, and the volume exceeded 4 060 m ³.

  • Currently there is ongoing installation and monolithic works such as reinforcement of stairs and columns, columns concreting at -0.150, and ceiling formwork mounting.

You can see the dynamics of the 1.5 months of the construction (from August 1 to September 15) in our time-lapse video.

Proving its reputation of a reliable general contractor, LMS performs its obligations to the customers who entrust us again with the realization of their projects with high quality and in time.

Building a story, proud of the result!

The reinforcement of the frame of the future Voronezh Airport terminal continues-photo-1 The reinforcement of the frame of the future Voronezh Airport terminal continues-photo-2 The reinforcement of the frame of the future Voronezh Airport terminal continues-photo-3 The reinforcement of the frame of the future Voronezh Airport terminal continues-photo-4 The reinforcement of the frame of the future Voronezh Airport terminal continues-photo-5 The reinforcement of the frame of the future Voronezh Airport terminal continues-photo-6 The reinforcement of the frame of the future Voronezh Airport terminal continues-photo-7 The reinforcement of the frame of the future Voronezh Airport terminal continues-photo-8