In September, the monolithic works was completed at the «below zero» level in the Esplanada shopping center

09.10.2020

Multifunctional complex «Esplanada» will place completely new spaces for Perm: halls for events for up to 1000 people international level, a five-star hotel under a global brand, a restaurant overlooking the city, the only multi-level underground parking in the city center for 1500 cars and a shopping gallery.

In September, LMS company, as the general contractor completed in-sotu concrete works at the «under zero» level, including construction of an underground parking lot.

The monolithic works was completed in the Esplanada center - Photo 1

Construction is being carried out at several levels at once and is being carried out ahead of schedule: at the level of 5.75 m the monolithic works of the first floor continues, at the level of 11.5 m construction of columns is in process.

In October construction of brickwork for the future shopping center will continue. Builders perform work on pouring concrete walls, reinforcement, formwork set and monolithic erection of floors and columns on the first floor of the building.

The monolithic works was completed in the Esplanada center - Photo 2

The monolithic works was completed in the Esplanada center - Photo 3

The works on fire protection system (AUPT) have begun .

LMS values ​​its reputation as a reliable general contractor, the company has repeatedly confirmed its status by implementing a number of complex, priority, breakthrough infrastructure projects.