Shopping center «Nebo»: a number of finishing works have been completed

05.07.2021

The partitions of gas concrete blocks and bricks are fully prepared and 92% of the partitions of drywall in tenant zones have been completed at the site. The specialists of the LMS Group of Companies have finished the decoration of stairwells, have fulfilled the tightening and laying of tiles.

75% electrical and mechanical works completed, 95% roof insulation completed. Ventilation and central air-conditioning systems are ready.

Let us remind, the final stage of the work on the project of construction of the shopping center «Nebo» in Moscow includes the installation of facades with elements of stained glass (88%), the arrangement of all engineering systems of the building (75%), roofing works (95%), as well as the works on landscaping (82%).

The frame of the building «Nebo» is erected on the building area of 13 370 m2. 31,000 m3 of reinforced concrete and 358 tons of metal structures are involved. The area of the building is 50 533 m2.

Customer of the project - managing company «Stolitsa Management». The term of the project is September 2021.

LMS group of companies, confirming its reputation as a reliable general contractor, satisfies its obligations to customers on time, who are satisfied with it, trust us over and over again with realization of their projects.

Nebo: a number of finishing works have been completed - Photo 1

Nebo: a number of finishing works have been completed - Photo 2

Nebo: a number of finishing works have been completed - Photo 3

Nebo: a number of finishing works have been completed - Photo 4

Nebo: a number of finishing works have been completed - Photo 5

Nebo: a number of finishing works have been completed - Photo 6