Сhronicle of construction in 2021: Simvol Residential Complex in Moscow

29.12.2021

The general contractor, the LMS Group of Companies, implements a multifunctional complex residential building with underground parking (line «2B», residential complex «SIMVOL», buildings 16-18). The general contractor develops working documentation, BIM-model, performs construction-installation, finishing and beautification works. Completion of construction is in 2023.

About the project:

The customer is Don-Stroy Invest JSC.

The technical customer is Generalnaya Directsiya «Centr» JSC.

Technical data:

  • Total area of the facility — 93 729 m2
  • 3 buildings — 16, 17 and 18 corps
  • 27 floors, 992 flats and 449 parking places in a two-level underground parking area.

The inner courtyard of the houses is fenced off and equipped with vehicle access control through the checkpoints. It is intended to place:

  • an integrated supermarket;
  • built-in a physical culture and health improvement complex;
  • catering establishments with up to 50 seats each;
  • office space.

April

Donstroy, the leading development company of Moscow chose the general contractor of 16-18 buildings of the Simvol residential complex.

Сhronicle of construction in 2021: Simvol in Moscow - Photo 1

Сhronicle of construction in 2021: Simvol in Moscow - Photo 2

May

The general contractor mobilized the construction site at the facility: a canteen building for workers and IT engineers was built in a short period of time. The construction of the administrative and household building was in progress. The system of temporary water supply, sewerage and electricity were connected. Excavation work was underway on the pit.

Сhronicle of construction in 2021: Simvol in Moscow - Photo 3

Сhronicle of construction in 2021: Simvol in Moscow - Photo 4

June

The mobilization phase at the site has been completed. Residential and administrative buildings for workers, engineers and technicians were built. Power supply systems, water supply, office and air-conditioning were connected. Excavation work on the site has been completed at 51%. Hydroinsulation of the foundation was 15%. A total of 69% of the work was carried out on scarf fences. Work was done on the first concrete filling under the foundation.

Сhronicle of construction in 2021: Simvol in Moscow - Photo 5

July

Work was continuing on the construction of the foundation of constructing buildings 16, 17, 18 of the residential complex Simvol in Moscow.

The General Contractor carried out 63% of the excavation work. The production of hydro-insulation of the foundation is 20% ready. The work on casing fences is being completed (83%) and 566 splints are slaughtered.

Work was carried out to fill the foundation — the construction of a monolithic slab. For the foundation, 342 tons of reinforcement were used, for pouring – 2 855 m³ of concrete.

Сhronicle of construction in 2021: Simvol in Moscow - Photo 6

August

In the 17th and 18th buildings, a zero level of pouring concrete foundations has been achieved. This implies the beginning of the stage of work on the erection of the supporting structures of the future structure. Also, in these buildings, works on the installation of sheet piling have been completed (100%). Work is actively underway to waterproof the building's foundation.

Сhronicle of construction in 2021: Simvol in Moscow - Photo 7

September

At the construction site of the 17th and 18th buildings, a zero level of pouring concrete foundations has been achieved. Also, the installation of sheet piles has been completed, 100% of the sheet piles were hammered.

Excavation works have been completed at the site of the 16th building. The pioneer foundation slab of the future building is also poured. In the process of pouring the columns and walls of the future parking lot of the 16th building.

At the construction site of the 18th building, work continues to strengthen the walls of the excavation with a spacer system - a structure made of metal pipes.

Сhronicle of construction in 2021: Simvol in Moscow - Photo 8

Сhronicle of construction in 2021: Simvol in Moscow - Photo 9

October

The excavation on three buildings is 87% complete, and the installation of spacer systems is close to 54% readiness. Work is underway to fill the foundation in different areas. On the site of the 16th and 17th buildings, concreting is carried out on 2 floors. Also, work is being done on waterproofing the foundation and laying a protective screed.

Сhronicle of construction in 2021: Simvol in Moscow - Photo 10

Сhronicle of construction in 2021: Simvol in Moscow - Photo 11

November

Work was underway to fill vertical structures and floor slabs of future buildings.The installation of vertical structures was performed at the level of the first floor on the site of the building 18. Floor slabs were installed at the level of the third floor (+15.45) on the site of the building 17.

The installation of reinforced concrete structures of the building continued on the territory of building 16 on the minus 2nd and minus 1st floors. The laying of brick walls continued (below the 0.00 mark) in the future parking lot of the residential complex. The foundation has been completed throughout the entire facility.

Сhronicle of construction in 2021: Simvol in Moscow - Photo 12

Сhronicle of construction in 2021: Simvol in Moscow - Photo 13

December

On the site of the building 18 at the level of the technical floor, the installation of vertical structures was performed. The installation of floor slabs on the 2nd floor was continued.

On the territory of the 17th building, reinforced concrete work continued.

In building 16, specialists carried out the installation of vertical structures on the 1st floor.

On the site of the stylobate, the laying of walls from aerated concrete block began. At the parking lot, work continued on the brickwork at the mark below 0.

Сhronicle of construction in 2021: Simvol in Moscow - Photo 14

Сhronicle of construction in 2021: Simvol in Moscow - Photo 15

Сhronicle of construction in 2021: Simvol in Moscow - Photo 16