About the construction of the Eastern exit to the highway «M-5» Ural from Ufa

15.03.2021

The implementation of the first stage of the project «New exit from Ufa to the federal highway M-5 «Ural – the Eastern exit» continues.

The team of LMA LLC is constructing a road tunnel with a length of 1249 m. The tunnel includes two two-lane tunnels with a length of 1.2 km. The width of the road will be 8.5 m x 2.

At the moment, the builders are carrying out work on the sinking: the callotnaya (upper) part of the Northern Tunnel with a protective screen made of pipes; the strauss (lower part)and the tray part of the Northern Tunnel with a temporary support.

In parallel, reinforcement is carried out within the framework of the device of the lower part of the central support. Reinforcement, installation of the formwork and concreting of the upper part of the central support are carried out.

Work on the sinking and installation of temporary support for the Northern and Southern adits is actively progressing. The central tunnel is being drilled in the opposite direction towards the Eastern Portal.

In addition, preparations for the work on the South Tunnel are continuing: engineering networks are being rebuilt, a ramp is being built, etc.

Recall that the completion date is September, 2023.

Project customers: The Republic of Bashkortostan represented by the State Committee for Transport and Road Management, LLC «Bashkir Concession Company».