In September, the construction of the new air terminal complex of Voronezh International Airport continued according to the approved schedule.

Specialists of LMS Group, the general contractor, are installing and reinforcing the formwork of floor slabs at +5.250 level. 2,500 m² of installation work has been carried out. For this, 30 tons of reinforcing steel were used.

At the elevation -0.150, 230 m³ of concrete were poured for installation of formwork and concreting of columns and walls. The works on laying the internal drainage system are 20% complete.

Confirming its reputation of a reliable general contractor, LMS fulfills its obligations to the customers, who again entrust us with the implementation of their projects.

Build the history, proud of the result!

Construction of the terminal at Voronezh airport is gaining momentum-photo-1 Construction of the terminal at Voronezh airport is gaining momentum-photo-2 Construction of the terminal at Voronezh airport is gaining momentum-photo-3 Construction of the terminal at Voronezh airport is gaining momentum-photo-4 Construction of the terminal at Voronezh airport is gaining momentum-photo-5 Construction of the terminal at Voronezh airport is gaining momentum-photo-6 Construction of the terminal at Voronezh airport is gaining momentum-photo-7