The construction of the Mall «Kuzminki» in Moscow was completed on 18%

31.01.2023
Video

The general contractor LMS Group of Companies is rapidly implementing the construction of a new Multifunctional mall Kuzminki in Moscow.

At the end of January, the progress of work at the facility was 18%. Monolithic works were carried out in a volume of 20,550 m3. Waterproofing of monolithic structures is ready on an area of 17,850 m2.

LMS specialists have already completed the concreting of the floor slab of the third floor of the 2nd block.

The following types of work are continuing at the site:

  • installation of vertical and horizontal pasting waterproofing;
  • the device of concrete preparation and cement-sand screed under the foundation plate of the 1st block;
  • installation of the foundation plate of the 1st block;
  • installation of the formwork of the floor slabs of the third and fourth floors;
  • reinforcement and concreting of the floor slabs of the second and third floors of the 3rd block;
  • reinforcement and concreting of the floor slab of the fourth floor of the 2nd block;
  • reinforcement and concreting of vertical structures of the second and third floors.

Large construction equipment is working at the facility, 401 specialists of the general contractor are also employed.

The customer of the project is AStrade Group LLC.

Confirming the reputation of a reliable general contractor, LMS Group of Companies efficiently and on time fulfills its obligations to customers who trust us to implement their projects again.

The construction of the Mall «Kuzminki» in Moscow was completed on 18%-photo-1 The construction of the Mall «Kuzminki» in Moscow was completed on 18%-photo-2 The construction of the Mall «Kuzminki» in Moscow was completed on 18%-photo-3 The construction of the Mall «Kuzminki» in Moscow was completed on 18%-photo-4