The specialists of LMS, the general contractor of G-Drive Arena multifunctional complex, perform finishing works throughout the building.

Fences are being installed in the bowl, a subsystem for acoustic panels is being mounted, a metal frame for LED displays on the perimeter of the stands is being installed. The tests of the stationary fire robots were made.

There are 14 elevators and 8 escalators installed in the building. The installation of the engineering systems of fire fighting, ventilation, smoke removal, air conditioning, water supply and sewerage as well as the power and low voltage networks is going on. The building is connected to the city engineering networks of water supply and sewage, heat supply and communication networks.

On the adjoining territory the works on an accomplishment are finished: the paving tiles and illumination supports are placed, the greening is done. The installation of fencing has begun.

The technical readiness of the Arena is 84%.

G-Drive Arena construction: June results-photo-1 G-Drive Arena construction: June results-photo-2 G-Drive Arena construction: June results-photo-3 G-Drive Arena construction: June results-photo-4 G-Drive Arena construction: June results-photo-5 G-Drive Arena construction: June results-photo-6 G-Drive Arena construction: June results-photo-7 G-Drive Arena construction: June results-photo-8 G-Drive Arena construction: June results-photo-9