August results of Arena Omsk construction

03.09.2021

The construction of the Arena continues at all sites.

Inside of the building:

  • The assembly of the grandstands of the first tier has been completed. Work is underway at the level of the second tier.
  • Internal staircases are being installed, engineering networks are being installed, screed for 1–5 floors.
  • Internal partitions are mounted on the 1st - 4th floors. At the same time, surfaces are being prepared for finishing on the ground floor.

Outside of the building:

  • The load-bearing metal structures are being mounted for the first installation of the stained-glass window of the main building. The installation of the roof covering is in progress.

Landscaping:

  • At the same time, the landscaping of the parking area is being carried out. At two sites, the builders are laying the first layer of asphalt concrete pavement.
  • The installation of external engineering networks continues: heat supply, sewerage, communication networks, power supply and lighting.
August results of Arena Omsk construction-photo-1 August results of Arena Omsk construction-photo-2 August results of Arena Omsk construction-photo-3 August results of Arena Omsk construction-photo-4 August results of Arena Omsk construction-photo-5 August results of Arena Omsk construction-photo-6 August results of Arena Omsk construction-photo-7