Construction dynamics of Simvol Residential Complex in March

22.03.2022

Three buildings (16, 17 and 18) are being erected non-stop on the site of Simvol Residential Complex in Moscow. The specialists of the general contractor of the LMS Group of Companies continue the construction and installation works of the vertical structures and floor slabs.

The tenth floor of Building 18 has been reached. In the 17th block the works on the sixth floor are in progress. And in the 16th block the installation of the floor slabs of the technical floor is in progress. In the Sports and Recreation Center the builders are busy assembling the vertical structures and floor slabs on the second floor. The installation of walls of aerated concrete blocks is continuing on the fifth floor of Building 17 and on the eighth floor of Building 18.

On the territory of all three buildings of Simvol Residential Complex the assembling of prefabricated reinforced concrete stairs is in progress.

Living up its reputation of a reliable general contractor, LMS Group of Companies fulfills its obligations to customers up to the highest standard of performance and in due time, while the finally convinced customers trust us again to implement their projects.

Construction dynamics of Simvol Residential Complex in March-photo-1 Construction dynamics of Simvol Residential Complex in March-photo-2 Construction dynamics of Simvol Residential Complex in March-photo-3 Construction dynamics of Simvol Residential Complex in March-photo-4 Construction dynamics of Simvol Residential Complex in March-photo-5