Construction dynamics of the Industrial Complex in Chernyakhovsk in November

29.11.2022

The specialists of the general contractor, LMS Group, are continuing at a rapid pace with the construction and finishing works at the Silicon Wafers (SW) and Photovoltaic Converters (PV) Industrial Complex in the Chernyakhovsk Industrial Park.

A set of construction measures for the installation of supporting structures is being completed at the site:

  • installation of sandwich panels of the outer contour of building No. 2;
  • Assembling of internal walls and partitions in building No. 2 is ready for 24%, No. 4 - 94%, No. 10 - 75%, No. 12 - 100%, No. 16 - 100%;
  • roofing work on buildings 2 - 90% and 4 - 82%;
  • the installation of monolithic reinforced concrete slabs in all buildings has been completed.

Work is continuing on the interior finishings:

  • plastering work is 93% complete;
  • floor screed has been completed;
  • gypsum board underlayment in Building 16 - 46%;
  • puttying and painting work 30% complete;
  • laying of ceramic tiles half completed;
  • works on installation of internal and external engineering systems are in progress.

The landscaping is underway: the installation of kerb stones is 55% complete, the base course for the site roads as well as the laying of geotextile, sand and crushed stone is 30% complete.

The customer of the project is EnCORE, which belongs to Unigreen Energy.

Confirming its reputation as a reliable general contractor, LMS Group fulfils its obligations to customers, who entrust us once again with the implementation of their projects.

Construction dynamics of the Industrial Complex in Chernyakhovsk in November-photo-1 Construction dynamics of the Industrial Complex in Chernyakhovsk in November-photo-2 Construction dynamics of the Industrial Complex in Chernyakhovsk in November-photo-3 Construction dynamics of the Industrial Complex in Chernyakhovsk in November-photo-4 Construction dynamics of the Industrial Complex in Chernyakhovsk in November-photo-5 Construction dynamics of the Industrial Complex in Chernyakhovsk in November-photo-6 Construction dynamics of the Industrial Complex in Chernyakhovsk in November-photo-7 Construction dynamics of the Industrial Complex in Chernyakhovsk in November-photo-8