November construction dynamics of 16-18 buildings of Simvol Residential Complex

09.11.2022

The general contractor LMS Group continues high-speed construction works in the Smelost quarter of the Simvol Residential Complex in Moscow.

Roofing works have been completed in Building 18, installation of insulation is 85% complete. LMS builders have installed more than 70% of the double-glazed windows in the building. The installation of stained-glass windows on the 1st and 2nd floors is in progress.

Plastering works in public spaces on floors 15-27 are in progress in Building 17. They have completed installation of glass units, waterproofing of the roof and floor screed and plaster works in the staircases and corridors on the floors.

LMS specialists have started installation of double-glazed windows and fiber-cement panels in the 16th building. The paving of the territory is in progress.

The installation of the floor screed with the toping in the underground parking zone, the installation of the facade heat insulation and the facade system guides, as well as the roof on the Sports and Recreation Center, the stylobate part and the underground parking zone, is going on at the construction site of three buildings. The installation of passenger elevators is in an active phase.

The customer of the project is DONSTROY Ltd.

Confirming its reputation as a reliable general contractor, LMS Group fulfills its obligations to the customers, who entrust us with the implementation of their projects.

November construction dynamics of 16-18 buildings of Simvol Residential Complex-photo-1 November construction dynamics of 16-18 buildings of Simvol Residential Complex-photo-2 November construction dynamics of 16-18 buildings of Simvol Residential Complex-photo-3 November construction dynamics of 16-18 buildings of Simvol Residential Complex-photo-4 November construction dynamics of 16-18 buildings of Simvol Residential Complex-photo-5 November construction dynamics of 16-18 buildings of Simvol Residential Complex-photo-6 November construction dynamics of 16-18 buildings of Simvol Residential Complex-photo-7 November construction dynamics of 16-18 buildings of Simvol Residential Complex-photo-8 November construction dynamics of 16-18 buildings of Simvol Residential Complex-photo-9