The management of Limak Holding and LMS inspected the construction of RC Simvol

22.06.2022

At the beginning of the week of June 20, the management of Limak Marash Group of Companies inspected the construction site of the 16th, 17th and 18th buildings of Simvol Residential Complex in Moscow and appreciated the fast pace of the project.

The meeting was attended by the Limak Marash GC’s members of the Board of Directors Bacaksiz Turhan Serdar and Gülseren Sinan Atalay, and the head of the Turkish Limak Holding – Nihat Özdemir. A tour of the site was conducted by Erdal Ural, the project manager.

What are the dynamics of construction of Residential Complex «Symbol» in June?

In Building 18th:

  • The installation of floor slabs and vertical structures on the 22nd floor continues.
  • The construction of the walls from aerated concrete blocks is continuing on the 17th floor.
  • The rough finishing work is continuing in the apartments, corridors and on the typical floors. Plastering in the hallways on the 13th floor is completed.
  • The assembly of the scaffolding has been completed and the installation of the facade thermal insulation has started.
  • The installation of the PVC windows has started.

In Building 17th:

  • Construction of the vertical structures of the 16th floor is in progress.
  • The installation of the walls of aerated concrete blocks on the 14th floor is in progress.
  • The installation of the scaffolding has been completed and the installation of the facade subsystem has started.

In Building 16th:

  • Construction of the vertical structures of the 14th floor continues.
  • The installation of walls from aerated concrete blocks on the 8th floor is in progress.
  • Plastering of the 10th floor corridors and staircases of the 5th floor is in progress.
  • The installation of the scaffolding is continuing and the installation of the facade subsystem has started.

The installation of monolithic stairs and staircases continues in three buildings. The installation of reinforced concrete structures is completed in the Sports and Recreation Center. The insulation of the roof on the stylobate has started. 
More than 6,120 tons of reinforcing steel was supplied for the construction of three buildings of the Symbol Residential Complex.

The commissioning of the Residential Complex Simvol is scheduled for the third quarter of 2023.

Confirming its reputation as a reliable general contractor, Limak Marash Group properly and on time fulfills its obligations to customers who have entrusted us again with the implementation of their projects.

The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-1 The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-2 The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-3 The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-4 The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-5 The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-6 The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-7 The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-8 The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-9 The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-10 The management of Limak Holding and LMS inspected the construction of RC Simvol-photo-11