Limak Holding and LMS management inspected the construction of the G-Drive Arena in Omsk

27.06.2022

The management of Limak Marash Group headed by Nihat Özdemir, Chairman of the Board of Directors of the Turkish Limak Holding, and members of Limak Marash Group Board of Directors, Bacaksiz Turhan Serdar and Gülseren Sinan Atalay, inspected the construction site of the G-Drive Arena in Omsk and appreciated the high pace of the facility.

»The technical readiness of the facility exceeds 80%. In spite of the fact that 2200 people are working at the facility, we will increase the pace in order to complete the construction within the period specified by the customer,» - Nihat Özdemir noted.

Currently, the building is finishing work: installing ceramic tiles, painting walls and ceilings.

The works on installing the ice field slab are completed. The installation of the engineering systems: fire fighting, ventilation, smoke exhaust, air conditioning, water supply and sewerage, power and low-current networks is continuing. Commissioning works have begun in some areas. The stands are equipped with fencing. The elevators and escalators are mounted.

Connections to urban utility networks such as water supply, sanitary sewerage, storm drainage, heating and communications are completed.

Works on landscaping, gardening and street lighting of the territory continue.

The site employs 2200 people, including the engineering staff.

Limak Holding and LMS management inspected the construction of the G-Drive Arena in Omsk-photo-1 Limak Holding and LMS management inspected the construction of the G-Drive Arena in Omsk-photo-2