Perm Gallery Construction Progress was 58% in August

25.08.2023

Specialists of the general contractor of the LMS Group of Companies the construction of a new building is being carried out at a high pace Perm State Art Gallery.

The installation of solid six-meter glass stained-glass windows and copper sheets of the facade of the new building was completed by 51%. Roofing works are completed by 62%.

Builders continue the following types of finishing works:

  • plastering works - 72%
  • floor screed - 95%
  • installation of drywall partitions - 55%

Infrastructure works have been completed by 45%: workers are installing household and storm sewers, outdoor water supply systems, as well as heating networks.

The number of specialists at the facility has reached 445 people, including IT specialists.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers who entrust us with the implementation of their projects again qualitatively and on time.

Perm Gallery Construction Progress was 58% in August-photo-1 Perm Gallery Construction Progress was 58% in August-photo-2 Perm Gallery Construction Progress was 58% in August-photo-3 Perm Gallery Construction Progress was 58% in August-photo-4 Perm Gallery Construction Progress was 58% in August-photo-5 Perm Gallery Construction Progress was 58% in August-photo-6 Perm Gallery Construction Progress was 58% in August-photo-7