The progress of work in the 16-18 buildings of the RC «Symvol» in May is 91.5%

15.05.2023
Video

The general contractor LMS Group of Companies is rapidly implementing the construction of a new Residential complex «Symvol» in Moscow.

Facade works in the 16th building have been completed, and in the 17th and 18th buildings are nearing completion. Overall, the progress of facade work was 89%.

Electrical work is 90% completed, and mechanical work is 92%. Technological equipment is installed at 35%. Elevators are installed at 95%, and doors at 90%.

Finishing works are completed by more than 80%. The water supply connection works have been completed. The marking and installation of limiters have been completed in the underground parking, and the installation of road signs has begun.

Landscaping and lawn laying are actively underway. Landscaping has been completed by more than 70%.

The customer of the project is LLC «Donstroy».

Confirming the reputation of a reliable general contractor, LMS Group qualitatively and on time fulfills its obligations to customers who trust us to implement their projects again.

The progress of work in the 16-18 buildings of the RC «Symvol» in May is 91.5%-photo-1 The progress of work in the 16-18 buildings of the RC «Symvol» in May is 91.5%-photo-2 The progress of work in the 16-18 buildings of the RC «Symvol» in May is 91.5%-photo-3 The progress of work in the 16-18 buildings of the RC «Symvol» in May is 91.5%-photo-4 The progress of work in the 16-18 buildings of the RC «Symvol» in May is 91.5%-photo-5 The progress of work in the 16-18 buildings of the RC «Symvol» in May is 91.5%-photo-6