The overall readiness of the Kuzminki Mall has reached 15%

15.12.2022

The general contractor LMS Group of Companies continues the implementation of the new Kuzminki Multifunctional Shopping Mall in Moscow at a high rate. From November to mid-December, the construction of the facility increased by 5%.

Monolithic works were carried out in a volume of 13,100 m3. Waterproofing of monolithic structures is ready on an area of 13,950 m2.

In some areas of the facility, LMS specialists have already completed concreting the floor slabs of the 1st and 2nd floors, as well as the vertical structures of the 1st floor.

At the moment, the following works are continuing at the site:

  • the device of vertical and horizontal pasting waterproofing;
  • installation of the floor slab formwork on the 1st and 2nd floors;
  • reinforcement and concreting of floor slabs and vertical structures (walls and columns) of the 1st and 2nd floors.

380 specialists, including engineers and technicians, are involved in the project.

The customer of the project is AStrade Group LLC.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to the customers, who entrust us with the implementation of their projects.

The overall readiness of the Kuzminki Mall has reached 15%-photo-1 The overall readiness of the Kuzminki Mall has reached 15%-photo-2 The overall readiness of the Kuzminki Mall has reached 15%-photo-3 The overall readiness of the Kuzminki Mall has reached 15%-photo-4 The overall readiness of the Kuzminki Mall has reached 15%-photo-5