A video about progress of the shopping center "Nebo" project
A video about progress of the shopping center "Nebo" project
19.04.2021
To date, progress in some of the construction works of the shopping center "Nebo" in Moscow has been as follows:
Installation of facade metal structures - 95%;
Installation of sandwich panels - 88%;
Partitions from gas concrete blocks - 97%
Brick partitions - 98%
Stairwell tube finish - 88%
Ground floor fixation - 98%;
Tiling - 45%;
Electrical and mechanical work - 29.5%;
Roof insulation 59%
Ventilation system and central air-conditioning - 45%;
Plaster work - 100%.
Limak Marash group of companies, confirming its reputation as a reliable general contractor, satisfies its obligations to customers on time, who are satisfied with it, trust us over and over again with realization of their projects.