Installation of metal structures and monolithic works in AVK Voronezh are completed

03.03.2023

The general contractor LMS Group of Companies continues to build a new terminal complex of domestic air lines of the Peter I Voronezh International Airport at a high pace.

In accordance with the schedule of work to date, the terminal has already installed partitions made of aerated concrete blocks, half-timbers, floor screed in the amount of 500 m2, metal frame of the roof of the building has been installed, profiled flooring and cornices have been laid, sandwich panels in the amount of 1845 m2 have been installed, tanks for local storm water treatment facilities have been installed.

The metal structures of the checkpoint building have also been installed, the exterior and interior walls, sandwich panels, plaster and exterior lighting are almost completely ready.

Now specialists are laying engineering networks, automatic fire extinguishing systems, smoke ventilation, a set of technical safety equipment.

Confirming the reputation of a reliable general contractor, LMS fulfills its obligations to customers qualitatively and on time, who again entrust us with the implementation of their projects.

Installation of metal structures and monolithic works in AVK Voronezh are completed-photo-1 Installation of metal structures and monolithic works in AVK Voronezh are completed-photo-2 Installation of metal structures and monolithic works in AVK Voronezh are completed-photo-3 Installation of metal structures and monolithic works in AVK Voronezh are completed-photo-4