Monolithic work at the facility in Chernyakhovsk is nearing completion

30.03.2022

The construction work is on schedule on the territory of the wafer and cell fab in the Chernyakhovsk Industrial Park in the Kaliningrad region.

Monolithic works are nearly completed at the site, the readiness is 80% at the end of March (without the slab on the ground).

On the territory of the Chernyakhovsk Industrial Park, specialists of the general contractor LMS Group of Companies continue assembling steel structures of the buildings of the industrial complex (25%), as well as buildings of the treatment facilities (93%) and the refrigeration center (3%).

At the silicon plates production and storage building the reinforcement of the floor slab of the growth hall (65%), installation of precast columns and basement panels (87%), concreting of columns (85%) and installation of waterproofing of reinforced concrete structures (85%) continue.

The builders continue backfilling of the silicon wafer production and storage buildings (70%), photovoltaic converters (95%) and the process gas supply and compressor unit (60%). Works on waterproofing of reinforced concrete structures and installation of socle panels are also in progress in the compressor building (64%).

The customer of the project is EnCore, a business unit of Unigreen Energy.

Monolithic work at the facility in Chernyakhovsk is nearing completion-photo-1 Monolithic work at the facility in Chernyakhovsk is nearing completion-photo-2 Monolithic work at the facility in Chernyakhovsk is nearing completion-photo-3 Monolithic work at the facility in Chernyakhovsk is nearing completion-photo-4 Monolithic work at the facility in Chernyakhovsk is nearing completion-photo-5