LMS completes installation of the roof base of the Perm Gallery building

03.03.2023

Specialists of the general contractor of the LMS Group of Companies are rapidly constructing the building of the Perm State Art Gallery. The overall progress of work at the facility is 35%.

The installation of the metal frame in the amount of 1990 tons has been completed. Work is underway to tighten high-strength bolts with controlled tension. The installation of the roof base from the profiled sheet is coming to an end – 3820 m2 has been completed.

At the same time, LMS specialists are carrying out construction work on three letters: letter O, letter C and letter N.

Work continues on masonry of external and internal walls made of foam block – 2030 m3 has been completed. The builders have started rough finishing – plastering the walls of the basement of the main building, 768 m2 has been completed.

239 specialists, including IT specialists, are involved in the facility. Large-sized construction equipment works.

Confirming the reputation of a reliable general contractor, LMS Group qualitatively and on time fulfills its obligations to customers who trust us to implement their projects again.

LMS completes installation of the roof base of the Perm Gallery building-photo-1 LMS completes installation of the roof base of the Perm Gallery building-photo-2 LMS completes installation of the roof base of the Perm Gallery building-photo-3 LMS completes installation of the roof base of the Perm Gallery building-photo-4 LMS completes installation of the roof base of the Perm Gallery building-photo-5