LMS continues to build monolithic structures in the Ostrov Residential Complex

16.11.2022

LMS Group, the general contractor, continues high-speed construction of the fifth quarter of Ostrov Residential Complex (buildings 1-8) in Moscow. Preparation of the construction site is fully completed. Concrete mixture has been laid in the amount of 15,590 m3, more than 1,550 tons of reinforcement steel has been used.

At the moment the following works are performed on the construction site:

  • On the territory of the underground parking the arrangement of floor slabs -2nd and -1st floors and vertical structures -1st floor continues.
  • In building No.1 the installation of walls and columns of the -1st floor has been completed. The floor slab of the -1 storey and the vertical structures of the -1 storey are being erected.
  • In buildings 2, 3, 4 and 8 the vertical structures of the -1st floor are being assembled and reinforced.
  • In buildings 5 and 6, LMS specialists have started works on foundation reinforcement.
  • In building №7 the preparation of the basement for the basement slab is in progress.

For the construction 730 specialists, including engineering personnel, were involved.

The customer of the project is Donstroy LLC.

Confirming its reputation of a reliable general contractor, LMS Group fulfills its obligations to the customers, who entrust us with the implementation of their projects.

LMS continues to build monolithic structures in the Ostrov Residential Complex-photo-1 LMS continues to build monolithic structures in the Ostrov Residential Complex-photo-2 LMS continues to build monolithic structures in the Ostrov Residential Complex-photo-3 LMS continues to build monolithic structures in the Ostrov Residential Complex-photo-4 LMS continues to build monolithic structures in the Ostrov Residential Complex-photo-5