LMS started cladding the facade of the passenger terminal at Novy Urengoy airport

29.07.2022

At Novy Urengoy Airport the specialists of LMS Group, the general contractor, continue the construction of the new passenger terminal.

Outside work has been completed on the roof and the installation of the exterior facade subsystem, as well as the treatment of the main metal structures with fire retardant composition. The mounting of the decorative facade lamellas is 70% ready. The builders of the general contractor started the cladding of the facade with the composite panels.

Inside the terminal, the painting of the walls and the laying of large-format tiles on the walls in the passenger waiting area have begun. LMS specialists will soon begin finishing the walls and partitions.

The laying of external utility networks of sewerage and drainage is 90% ready. The installation of the outdoor utility networks of water and heat supply is completed.

The land leveling and crushed stone laying for the improvement of the territory of the air terminal and asphalt laying on the parking lot and the access road have been started.

Confirming the reputation as a reliable general contractor, LMS Group fulfills its obligations to the customers, who entrust us again with the implementation of their projects with high quality and in time.

LMS started cladding the facade of the passenger terminal at Novy Urengoy airport-photo-1 LMS started cladding the facade of the passenger terminal at Novy Urengoy airport-photo-2 LMS started cladding the facade of the passenger terminal at Novy Urengoy airport-photo-3 LMS started cladding the facade of the passenger terminal at Novy Urengoy airport-photo-4 LMS started cladding the facade of the passenger terminal at Novy Urengoy airport-photo-5 LMS started cladding the facade of the passenger terminal at Novy Urengoy airport-photo-6 LMS started cladding the facade of the passenger terminal at Novy Urengoy airport-photo-7 LMS started cladding the facade of the passenger terminal at Novy Urengoy airport-photo-8 LMS started cladding the facade of the passenger terminal at Novy Urengoy airport-photo-9 LMS started cladding the facade of the passenger terminal at Novy Urengoy airport-photo-10