LMS started the installation of the steel structures of the roof of the Perm Gallery

29.09.2022

The specialists of LMS Group, the general contractor, continue to assemble the frame of the Perm State Art Gallery. The installation of the metal frame of the building roof has started, more than 720 tons of metal constructions have been installed.

By the end of September 5,750 m³ of the backfill had been completed. Earthworks continue.

At the mark below zero the concreting of the foundation slab, walls and columns is ready in the volume of 3,944 m³, at the mark above zero - in the volume of 520 m³. The installation of the monolithic slabs on the profiled sheet is in progress.

In parallel, the waterproofing of the building foundation and walls is being performed, the works are finished on the area of 5,050 m² In the basement of the building, the partition walls made of foam blocks are being erected.

More than 180 specialists, including engineering personnel, are working on the construction site.

Confirming its reputation of a reliable general contractor, LMS Group fulfills its obligations to the customers, who entrust us again with the implementation of their projects.

LMS started the installation of the steel structures of the roof of the Perm Gallery-photo-1 LMS started the installation of the steel structures of the roof of the Perm Gallery-photo-2 LMS started the installation of the steel structures of the roof of the Perm Gallery-photo-3 LMS started the installation of the steel structures of the roof of the Perm Gallery-photo-4 LMS started the installation of the steel structures of the roof of the Perm Gallery-photo-5 LMS started the installation of the steel structures of the roof of the Perm Gallery-photo-6