The roof frame for the «Arena Omsk» will soon arrive at the construction place

12.02.2021

A metal frame weighing two thousand tons for the roof of the «Arena Omsk « will be brought to the construction site in March.

Omsk Plant of Metal Structures-Metal started work in December last year , and now almost completed the manufacture of the frame for the roof of the multifunctional sports center. The experts of the Federal Competence Center helped the factory workers to free up their capacities, analyzing the work of the enterprise and significantly simplifying the process of assembling parts. About 200 people are engaged in the assembly of more than a hundred structures every day.

- We have set a goal for ourselves - to pick up the order at any cost, even at a loss. «Fell» on the tender and these metal structures were left in Omsk. We support Avangard, we are patriots of the city and the hockey team, - Sergey Kuropatkin, General Director of OmZM-Metal, comments in the news of Channel 12 (Omsk Regional Television).

In January, the construction of the reinforcement frame, concreting of columns and walls on the first floor continued on two sections of the Omsk Arena. LMS specialists carried out the installation of a reinforcement frame, concreting columns and walls on the second floor floor slab in three sections. The delivery of elements of load-bearing metal structures of the roof has begun: to date, almost 800 tons have been delivered..

Recall that the completion date is September 2022.

The LMS company, which is leading the construction of the facility, has established itself as a reliable general contractor. The company's portfolio of implemented projects includes the construction of international airports in Rostov-on-Don, Volgograd, Khabarovsk, Chelyabinsk, as well as other infrastructure facilities in Russia.