Results of the second month of construction of the new terminal at Khabarovsk airport

01.11.2021

Exactly two months have passed since the start of the construction of the new Khabarovsk Airport Terminal of International Airlines. 60 days of construction in numbers and facts:

  • Earthworks are in progress at the construction site, 33,000 m3 of soil has been produced.
  • Work continues on the installation of piles — 578 of 605 driven piles and 21 of 24 bored piles have been installed.
  • The last stage of work is underway to remove communications from the construction zone.
  • Static and dynamic tests of all pile structures have been completed.
  • The works on pouring the grillages are in progress - 99 out of 128 grillages have been worked out, 560 m³ of concrete are poured.
  • Work continues on the pouring of vertical structures on the first floor - 34 units of structures have been installed, 104 m³ of concrete have been produced.
  • Work is underway on the waterproofing of the grillage, as well as backfilling of the pit sinuses.
  • Work has begun on the preparation of the foundations for the floor slab, and pouring will begin in the coming days.
  • A pit for a tower crane has been developed; in the coming days, they will start pouring the foundation.
  • There are 330 people on the construction site.

The general contractor for the construction is LMS LLS.

This is already the second project of joint cooperation with the customer — JSC Khabarovsk International Terminal. The first project was the construction of a passenger terminal for domestic airlines at Khabarovsk International Airport.

Results of the second month of construction of the new terminal at Khabarovsk airport-photo-1 Results of the second month of construction of the new terminal at Khabarovsk airport-photo-2 Results of the second month of construction of the new terminal at Khabarovsk airport-photo-3 Results of the second month of construction of the new terminal at Khabarovsk airport-photo-4 Results of the second month of construction of the new terminal at Khabarovsk airport-photo-5 Results of the second month of construction of the new terminal at Khabarovsk airport-photo-6