Construction readiness on the «East road» in Ufa

09.08.2021

By early August, the overall readiness of the bridge across the Ufimka River on the Vostochny Exit project exceeded 20%, as reported by the Ministry of Transport and Roads of the Republic of Bashkortostan. At the moment, the entire range of works on the installation of supports is being carried out on the construction of the flyover and bridge crossing.

LMA specialists at the construction site note that the scope of work performed on the construction of the overpass includes:

  • plugging of the soil is 67% completed;
  • installation of grillages is 45% complete;
  • the concreting of the columns of the overpass supports is also completed by 45%;
  • completed 28% of the work on the installation of crossbars;
  • forty-five 33-meter prefabricated reinforced concrete beams of the flyover span were produced.

At the site of the eastern portal, which belongs to the construction of the tunnel, work is being actively carried out on waterproofing the foundation. The readiness of the waterproofing device is 50%.

The cutting of the vegetation layer of the soil has been completed at the Vostochny exit site. More than 528,000 m³ of excavation has already been completed. The work continues dynamically.

LLC «LMA», part of the LMS Group of Companies, maintains a table of the open-pit mine for the given object on its own. According to preliminary estimates, the quarry has a volume of 2.4 million m³. Sand and gravel mixture is used for the manufacture of mortars - this is an excellent material for the construction of roads.

Confirming the reputation of a reliable general contractor, LMS Group of Companies fulfills its obligations to customers with high quality, who trust us again and again for their projects.