Year of construction of the new terminal at Novy Urengoy airport

23.12.2021

Exactly a year ago, on December 22, 2020, the construction of a new passenger terminal at Novy Urengoy airport was officially launched.

Governor of Yamalo-Nenets Autonomous Okrug Dmitry Artyukhov and General Director of Airports of Regions Management Company Evgeny Chudnovsky took part in the solemn ceremony of the start of large-scale construction work.

During the year we have been building a new modern passenger terminal. And today, summing up the intermediate result, we can confidently say that we have crossed the halfway point of the construction site, the terminal is more than 50% ready.

The specialists of the general contractor, the LMS Group of Companies, have erected the frame of the building, are completing the installation of the roof, and have begun glazing. Work is also underway inside the building – everything is in accordance with the approved schedule.

The completion date is December, 2022.