At the construction site of the new passenger terminal of Novy Urengoy Airport, specialists of LMS Group, the general contractor, started treating the main metal structures with fire retardant.

The installation of the exterior facade structure is nearing completion, 90% readiness.  The installation of the metal constructions of the entrance groups is completed. All the sectional doors in the airport (7 units) are installed.

The laying of large-size floor tiles continues in the terminal. The installation of the ventilation air ducts and the smoke preventing system is almost finished. 80% of the air ducts are ready to be installed.

Confirming its reputation of a reliable general contractor, LMS Group fulfills its obligations to the customers, who entrust us again with the realization of their projects with high quality and in time.

Translated with www.DeepL.com/Translator (free version)

Confirming its reputation as a reliable general contractor, LMS Group properly and on time fulfills its obligations to customers who have entrusted us again with the implementation of their projects.

Dynamics of the Novy Urengoy airport terminal under construction in June-photo-1 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-2 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-3 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-4 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-5 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-6 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-7 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-8 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-9 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-10 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-11 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-12 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-13 Dynamics of the Novy Urengoy airport terminal under construction in June-photo-14