Construction dynamics of Novy Urengoy airport terminal in September

16.09.2021

Work is in full swing at the construction site of the new passenger terminal. LMS specialists are making efforts to close the thermal circuit of the building before the onset of cold weather.

  • The installation of metal structures is 83% completed. Over 1,500 tons of metal will be used for the installation of the metal frame of the building.
  • The builders are assembling trusses and roof elements, and have started assembling galleries and stairs.
  • The construction of the floor slab on the second floor has been done. Pouring of concrete on the third (technological) floor will soon be completed.
  • The work involved 30 units of units of equipmentand more than 400 workers.