Construction dynamics of the fifth block of Ostrov Residential Complex in Moscow

06.09.2022

Specialists of LMS Group continue to build the fifth block of Ostrov Residential Complex (1-8 blocks) in Moscow by the order of Donstroy.

The mobilization of the construction camp continues on the territory. 430 employees, including engineering and technical personnel, are involved in the works at the site. Large construction equipment is used at the site: three mobile cranes, four excavators and a forklift.

At the moment the following works are carried out on the site:

  • Manual revision of soil for foundations.
  • Waterproofing under the foundation slabs.
  • Ultrasonic testing of waterproofing.
  • Foundation reinforcement of Building 2.
  • Laying of the gravel basement with compaction and geotextile laying.

Proving its reputation of a reliable general contractor, LMS Group performs its obligations to the customers, who entrust us with the implementation of their projects with high quality and in time.

Construction dynamics of the fifth block of Ostrov Residential Complex in Moscow-photo-1 Construction dynamics of the fifth block of Ostrov Residential Complex in Moscow-photo-2 Construction dynamics of the fifth block of Ostrov Residential Complex in Moscow-photo-3