Construction dynamics of the new terminal of Novy Urengoy Airport, October 2021

08.10.2021

The installation of the metal structures of the new passenger terminal is 99% complete; over 1,500 tons of metal have been used for the installation of the building's metal frame.

The builders of LMS have completed the installation of floor trusses, are installing roofing elements, have begun to install galleries and stairs, and install sandwich panels on the facade. Completed devices for floor slabs on the second and third (technological) floors.

Work is being completed on laying communications to the terminal: a heating system, water supply and power supply lines.

The work involved 30 units of large equipment and more than 400 workers of the general contractor.