The general contractor, LMS Group of Companies, is rapidly building a new airport complex at Magadan International Airport.
At the moment, general construction works are being carried out at the facility:
- Monolithic works are 100% completed.
- The installation of metal structures is 99% complete.
- The installation of half-timbered metal structures is 82% complete.
- Profiled flooring is 87% complete.
- Installation of a soft roof is completed by 10%.
- Installation of sandwich panels is completed by 23%.
Electromechanical work is carried out on the networks at the facility:
- Installation of electric trays is completed by 27%.
- The automatic fire extinguishing system is 20% complete.
- The duct system is 38% complete.
- The water supply and sewerage system is 11% complete.
- The heating system is 29% complete.
Finishing and facade works are being carried out:
- Finishing works are completed by 15%.
- Partitions made of wall blocks by 75%.
- Partitions according to the Knauf system by 25%.
- Facade work is 35% completed.
There are 425 specialists involved at the site, including engineering and technical staff. Large construction equipment is working.
Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.