Dynamics of Voronezh airport construction in the first decade of January

12.01.2024

The LMS Group of Companies, the General contractor, continues to build a new airport terminal complex for domestic air lines of the Peter I Voronezh International Airport at a high pace.

At the beginning of 2024, they have been fully completed:

  • roofing works - 100%
  • installation of stained glass windows - 100%

During the New Year holidays, interior finishing works were actively carried out at the construction site: in the bathrooms, the walls, floors and ceilings were completely finished with granite. Work on the installation of suspended ceilings is also continuing (in general, these works were completed by 60%) - 15% of the total volume was completed during the holidays. The preparation of auxiliary structures for stained glass partitions and fences is actively underway.

During the same period, work was carried out on the installation of power supply systems, automatic irrigation, fire extinguishing, ventilation, heating, air conditioning, as well as the connection of fire protection systems, sound information, electric lighting, security alarm systems.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who again entrust us with the implementation of their projects.