Dynamics of bridge works at the Eastern exit from Ufa in March

13.03.2023
Video

The general contractor for the construction of the Eastern Exit from Ufa to the Federal Highway M-5 Ural – LLC «LMA», part of the LMS Group of Companies, announced that bridge work is on schedule.

Watch the video of the progress of bridge work on the construction of the Eastern Exit from Ufa in March 2023.

The implementation of the project for the construction of a regional highway of the Republic of Bashkortostan «New exit from Ufa to the federal highway M-5 Ural – Eastern Exit» includes three large-scale stages.

The first stage is a road tunnel, which includes two tunnels 1.2 km long, with two lanes in each. The width of the road will be 8.5 m x 2.

The second stage is a steel bridge over the Ufa River with a length of 470 m and an overpass with a length of 2,200 m, with two two-lane platforms. The width of the roadway will be 27.7 m.

The third stage is a 12 km long highway with four lanes. The category of the road is IB (express). The width of the road is 26 m .

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers qualitatively and on time, who again entrust us with the implementation of their projects.

Dynamics of bridge works at the Eastern exit from Ufa in March-photo-1 Dynamics of bridge works at the Eastern exit from Ufa in March-photo-2 Dynamics of bridge works at the Eastern exit from Ufa in March-photo-3 Dynamics of bridge works at the Eastern exit from Ufa in March-photo-4 Dynamics of bridge works at the Eastern exit from Ufa in March-photo-5