Results of the first month of construction of the new terminal at Khabarovsk airport

01.10.2021

Exactly one month has passed since the start of the construction of the new Khabarovsk Airport Terminal of International Airlines. 30 days of construction in numbers and facts:

  • Dismantling of asphalt concrete sidewalks and driveways was completed, fencing of the construction site was installed. 10,000 m of sidewalks and concrete pavements were dismantled.
  • The specialists mobilized the construction site.
  • Installation of the fence of the site of the object is ready an object.
  • Fencing of the facility territory is ready.
  • Wheel washer at the construction site was installed.
  • Access to the construction site is carried out through the checkpoint and only according to individual cards.
  • Earthworks are in progress at the construction site, 23,000 m3; of soil has been produced.
  • Work continues on the installation of piles — 417 driven piles and 21 bored piles have been installed.
  • Work is underway to remove communications from the construction area.
  • Static and dynamic load tests of pile structures are underway. The test period is 3-5 days. 160 tons are a load on one pile. The pile length is 12 m.
  • There are 300 people on the construction site (90 are actively working, and 210 are awaiting a patent).

The general contractor for the construction is LMS LLS. This is already the second project of joint cooperation with the customer — JSC Khabarovsk International Terminal. The first project was the construction of a passenger terminal for domestic airlines at Khabarovsk International Airport.