The General contractor LMS Group of Companies demonstrates the dynamics of the phased reconstruction of the existing airport terminal complex of international/domestic air lines at Tyumen International Airport (Roshchino).

At the moment:

  • Fully completed installation of free-standing foundations (100%).
  • The basement foundation.
  • Vertical structures of the basement were installed (100%).
  • The floor slab was installed at 0.150 marks, as well as brickwork in the basement (100%).
  • Soil development in the volume of 29,500 m3 (100%).
  • The vertical structure was installed above the mark - 0.150 (100%).
  • Backfilling of the total volume was performed (100%).
  • The vertical structure was installed above the mark + 4.650 (100%).
  • The floor slab was installed at the mark + 4.650 (100%).
  • The floor slab was installed at the level of + 9.900 (100%).
  • Masonry of brick partitions in the basement was completed (100%).
  • Masonry of aerated concrete blocks of partitions in the basement was completed (100%).
  • Masonry of facade aerated concrete blocks of the first floor was completed (100%).
  • Masonry of brick partitions on the ground floor was completed (100%).
  • Masonry of aerated concrete blocks of the first floor was completed (100%).

At the moment, the following works are underway at the facility:

  • 10459 m3 of concrete mix was laid, which is 99% of the total volume.
  • Installation of metal structures is 100% complete.
  • Floor screed is 100% completed in the basement.
  • The partitions made of GKL in the basement are 95% made.
  • The masonry of the aerated concrete blocks of the second floor is completely completed.
  • The masonry of aerated concrete blocks on the third floor is 100% complete.
  • On the ground floor there is a floor screed for 92%.
  • The masonry of the brick parapets on the roof is 100% complete.
  • Plastering works in the basement have been completed by 97%.
  • Plastering works on the ground floor have been completed by 22%.
  • The partitions made of GKL on the ground floor are 84%.
  • The partitions made of GKL on the second floor are 83%.
  • The porcelain stoneware of the basement is 47%.
  • Facade glazing is completed by 30%.
  • The vent facade is designed for 60%.
  • Roofing works have been completed on 7%.

Network work is being carried out (electromechanical work):

  • The electric trays in the basement are 92%.
  • The electrical trays of the first floor of the part are made to 92%.
  • General exchange ventilation of the basement is 92% complete%.
  • The general exchange ventilation of the first floor is 72%.
  • The general exchange ventilation of the second floor is 40% complete%.
  • Smoke ventilation in the basement is 88% complete%.
  • The AUPT of the basement is 78% complete.
  • AUPT of the first floor is 80% completed.
  • The heating of the first floor is 10% complete.
  • The sewer networks of the basement are 88% complete.
  • Low-current systems (mortgages) of the first floor are 75% complete.
  • Low-current systems (mortgages) of the basement are 100% complete.

407 specialists, including engeneers, are involved at the site.

Confirming the reputation of a reliable general contractor, LMS Group fulfills its obligations to customers with high quality and on time, who entrust us with the implementation of their projects again.

Dynamics of the construction of a new Roshchino Airport in Tyumen in April-photo-1 Dynamics of the construction of a new Roshchino Airport in Tyumen in April-photo-2 Dynamics of the construction of a new Roshchino Airport in Tyumen in April-photo-3 Dynamics of the construction of a new Roshchino Airport in Tyumen in April-photo-4 Dynamics of the construction of a new Roshchino Airport in Tyumen in April-photo-5 Dynamics of the construction of a new Roshchino Airport in Tyumen in April-photo-6 Dynamics of the construction of a new Roshchino Airport in Tyumen in April-photo-7 Dynamics of the construction of a new Roshchino Airport in Tyumen in April-photo-8 Dynamics of the construction of a new Roshchino Airport in Tyumen in April-photo-9 Dynamics of the construction of a new Roshchino Airport in Tyumen in April-photo-10